Start Date
|
End Date
|
Title
|
Location
|
Maintenance
|
Impact
|
SPW
|
|
4/15/2026
|
11/1/2026
|
Station Automation
|
Twelve Mile Compressor
|
Integrity Work
|
1
|
|
|
7/15/2026
|
7/15/2028
|
Shattuc Turbine Modernization
|
Shattuc Turbine
|
Other
|
1
|
|
|
8/24/2026
|
10/23/2026
|
ML2 Class Location Relay
|
Pipe - Twelve Mile
|
Integrity Work
|
1
|
|
|
10/12/2026
|
10/16/2026
|
A127 ECDA
|
Pipe - Columbia
|
Digs
|
1
|
|
|
10/13/2026
|
10/14/2026
|
ML3 cleaning pigs Ft. Hill to Perryville
|
Pipe - Fountain Hill
|
Cleaning Pig
|
1
|
|
|
10/13/2026
|
10/14/2026
|
ML2 cleaning pigs Ft. Hill to Perryville
|
Pipe - Fountain Hill
|
Cleaning Pig
|
1
|
|
|
10/17/2026
|
10/26/2026
|
Columbia Isolation
|
Pipe - Columbia
|
ILI Pigging Project
|
1
|
|
|
10/19/2026
|
10/23/2026
|
A140 ECDA
|
Pipe - Columbia
|
Digs
|
1
|
|
|
10/20/2026
|
10/21/2026
|
Glendale Scrubber Filter Change
|
Glendale Compressor
|
Regular Maintenance
|
1
|
|
|
10/22/2026
|
10/22/2026
|
Emissions Test on #5 Engine JJJJ
|
Glendale Compressor
|
Emissions Testing
|
1
|
|
|
10/22/2026
|
11/5/2026
|
Wood River Isolation
|
Pipe - Columbia
|
ILI Pigging Project
|
1
|
|
|
10/22/2026
|
12/1/2026
|
Carlisle Air Compressor
|
Carlisle Station
|
Other
|
4
|
|
|
10/26/2026
|
11/4/2026
|
Unionville Fall Shut-In
|
Unionville
|
Annual Maintenance
|
8
|
73016
|
|
10/27/2026
|
10/29/2026
|
ALLN to Horseshoe Lake Pig
|
Pipe - Columbia
|
ILI Pigging Project
|
1
|
|
|
11/3/2026
|
11/3/2026
|
22x24x26" ALE Columbia M&R to Mo Gas ILI - GEO Tool
|
Pipe - Columbia
|
ILI Pigging Project
|
1
|
|
|
11/5/2026
|
11/5/2026
|
22x24x26" ALE Columbia M&R to Mo Gas ILI - MFL Tool
|
Pipe - Columbia
|
ILI Pigging Project
|
1
|
|
|
11/6/2026
|
11/7/2026
|
State Route 15 HDD isolation
|
Pipe - Columbia
|
ILI Pigging Project
|
1
|
|
|
11/9/2026
|
11/11/2026
|
Westline Maintenance pigging for upcoming ILI project
|
EGT DIXIE
|
Cleaning Pig
|
1
|
|
|
11/12/2026
|
11/20/2026
|
St. Louis Area Maintenance
|
Pipe - Columbia
|
Pipe Replacement
|
8
|
74625
|
|
12/1/2026
|
12/2/2026
|
ML2 Class Location Relay
|
Pipe - Twelve Mile
|
Pipe Replacement
|
1
|
|
|
12/1/2026
|
12/2/2026
|
ML1 Joachim Creek HDD
|
Bon Terre Tower
|
Pipe Replacement
|
1
|
|
|
12/1/2026
|
12/2/2026
|
Meramec Receiver Barrel & Piping Modifications
|
Pipe - Bonne Terre
|
Pipe Replacement
|
1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. No capacity impact
is expected at this time.
|
|
2. Coordinating with
necessary loads.
|
|
3. Based on historical
and current throughput, no capacity impact is expected. In the event
nominations increase significantly, restrictions may become necessary.
|
|
4. Coordinating
maintenance with interconnecting pipe to minimize customer impact. No
capacity impact is expected at this time; however, if operating conditions
change, affected parties will be notified.
|
|
5. Affected production
notified of shut-in during work.
|
|
6. Customers may
experience pressure fluctuations, but no capacity impact is anticipated.
|
|
7. Based upon customer nominations,
restrictions may become necessary.
|
|
8. Based on all
available information, capacity will be impacted. Capacity reductions will
be done in accordance with the provisions of MRT's tariff regarding
scheduling and interruption of services.
|